TÜV NORD India QA review

REQ-2026-00184 · KRL Global Equipment · Inspector INS-USA-1193 · Submitted 01 May 12:55 UTC

Awaiting QASLA remaining: 36hDocument completeness 92%Inspector response time: 1.4h

Draft report preview

v2 · Draft
TÜV NORD INDIA · INSPECTION REPORT
FAT Witness — Glycol Package
Report: RPT-2026-00184-v2
Date: 18 May 2026
Client
KRL Global Equipment Programme
Supplier
Houston Valve & Package Systems
PO
KRL-2026-INTL · PKG-MECH-04
Standard
ASME VIII Div 1; API 6D
Findings summary

FAT witnessed at supplier site. Hydrotest completed at 1.5× design pressure with no leakage detected. Functional cycle test passed. Minor cosmetic NCR raised on instrument bracket paintwork (NCR-001) — accepted with rework before shipment.

Checklist outcome
  • Supplier verified
  • PO match
  • Documents reviewed
  • Hold points witnessed
  • Photos captured
  • NCR logged (1 minor)
  • Outcome recorded
14 photos · 2 hydro charts · 1 NCR sheet attached

Inspector comments & NCR thread

INS-USA-1193
18 May · 16:42 CDT
Inspector
NCR-001: minor paint defect on instrument bracket. Supplier agreed rework prior to shipment, photos attached.
qa.reviewer3@tuvnordindia.com
01 May · 13:18 UTC
QA Reviewer · Internal — confidential
Please confirm rework completion photos are included in v3. Hydrotest chart legible — OK. Awaiting nameplate close-up.
INS-USA-1193
01 May · 14:02 UTC
Inspector
Acknowledged — uploading v3 with rework completion + nameplate macro.

Revision history

RPT-2026-00184
v1
Initial draft
RPT-2026-00184
v2
Awaiting close-out
RPT-2026-00184
Final
Pending QA approval